Kent sidewalk construction anything but smooth

Streetscape Building Committee Chairman Mike Gawel raised concerns about the construction choices being made and the lack of inspection by the engineering firm in the initial weeks of the project. He emailed the selectmen but the issue was not addressed by the board until a special meeting Aug. 22, after the cancellation of the board’s regular meeting on Aug. 18. Mike Doherty, the project manager from SLR Engineering, acknowledged to the Streetscape Committee on Aug. 12 that work at the beginning of the project had progressed faster than expected and that the engineers had been informed, so as of that date no inspections had been done. Since then, the inspector has been on site multiple times. Doherty explained that there were granite curbing supply issues that they became aware of during the bidding process and the bid documents were altered. In addition, Mather Corporation was unable to get suppliers in the northeast and had to get the granite from North Carolina. This was an additional $67,000 and the selectmen were aware of the change.

Kent sidewalk construction anything but smooth

Share This Article: