CTDOT Maintains Through Streets for Stonington Viaduct Replacement

In an unexpected move, the state Department of Transportation told town officials on Monday that it plans to fully replace the 83-year-old Alpha Street viaduct while preserving the through streets running below it. The new plan, dubbed “option five,” came after the department offered several repair options, including a $25.5 million bridge replacement that would have closed off Cutler Street and parts of Main and Matthews streets, First Selectman Danielle Chesebrough told CT Examiner. The 625-foot bridge, known as the Frank Turek viaduct, traverses Amtrak tracks and has provided the only vehicular access to Stonington Borough since 1940. The cost of “option five” has yet to be determined, but the town’s budget is capped at $1.2 million, Chesebrough said. Federal funds will supply 80 percent of the total, with the remainder paid by the state, according to a June 6 DOT presentation.

CTDOT Maintains Through Streets for Stonington Viaduct Replacement

Share This Article: