Lyme and Old Lyme voters approve extra $880K for senior center renovation

Voters in Lyme and Old Lyme on Monday decisively approved spending $880,000 more than the $5.3 already approved for the Lymes’ Senior Center renovation project. Old Lyme is responsible for $660,000 of the supplemental cost, while the smaller town of Lyme is responsible for $220,000. Officials in the two towns were scrambling earlier this year after learning the project was about $1.3 million over budget. But the committee in a project update said architecture and construction management firms assigned to the project have identified about $600,000 in savings. According to minutes from Lyme’s special town meeting, the project is currently slated to break ground on May 6. Doors are estimated to reopen at the renovated facility on March 1, 2025.

https://www.theday.com/local-news/20240416/lyme-and-old-lyme-voters-approve-extra-880k-for-senior-center-renovation/

Share This Article: