Excavators made methodical work knocking down the former Subway headquarters on Thursday, a job expected to take about three weeks. The company moved to nearby Shelton last October. As of Thursday, about 10 percent of the main building was down and a maintenance building was gone, said Andy Howard, a project manager from Scinto’s construction company, which began the site work on March 9. The work was going well, said Howard. Like Shimko, he said he was hopeful about the change. “I can see why some people don’t like us coming in here,” Howard said, “But the building is about 50 years old. It needs replacement or a lot of renovation.”