Crews are preparing to use explosives to blast away up to a foot of rock as part of the construction of a new crucial pumping station that will help mitigate flooding near the banks of the Housatonic River, according to the U.S. Army Corps of Engineers. The construction of the pump station is a key part of a new stormwater conveyance system that has been designed to handle what is expected to be a significant amount of rainwater runoff at the former Raybestos Memorial Field on Frog Pond Lane. The Environmental Protection Agency is using the once-abandoned softball field to consolidate tens of thousands of cubic yards of contaminated soil that was dumped across town by Raymark Industries, a defunct automotive parts manufacturer. The conveyance line is expected to be finished by this summer and the pump station is expected to be completed by mid-2024.