Town bodies approved $18.5 million for the project in 2017 and broke ground in 2018. “I’m proud to announce the Holland Hill project is completed,” Jason Li, the building committee chairman, told the selectmen in his final report on Monday. The committee was established in early 2016 to oversee the elementary school expansion project, which brought the enrollment capacity from a little more than 300 up to 504, removing the need for the portable classrooms. “We were fortunate enough we got this project done before the COVID pandemic hit,” he said. He said they plan on returning $115,000 to the town with the project coming in under budget and getting everything included on the initial charge.