Water main installation set to begin in downtown Naugatuck

The water company will be installing about six-tenths of a mile, or 3,300 feet, of water main on Church Street between Rubber Avenue and Division Street, Rubber Avenue between Water Street and Church Street, Barnum Court and Park Place. The price tag for the project is $2.4 million, which will be funded through the Water Infrastructure and Conservation Adjustment on customers’ bills, according to a press release on May 18. Work hours for the construction project will be from 7 a.m. to 4:30 p.m. during the weekdays, and the project is expected to be finished by August, according to the release. In February 2022 the Board of Mayor and Burgesses approved to contract with Kleinfelder Engineering, of San Diego, California to design storm water and sanitary sewer systems, offer construction oversight of the design, and to oversee a plan to repair, replace and improve those systems.

Water main installation set to begin in downtown Naugatuck

Share This Article: