A project to build a new middle school is estimated to cost as much as $21 million more than the amount approved by the town in referendum last June. The project, which was approved for $58.6 million in the referendum, is now estimated to cost nearly $80 million. $17.3 million is in additional construction costs, and $3.8 million is in soft costs. The construction increases include an increase in cost per gross square footage, escalation costs and “trade costs” — steel, HVAC, electrical, windows, roofing and other equipment. If the State of Connecticut approves the project, the town of Cromwell would be responsible for 60 percent of the increase — the state would cover 40 percent would come from the State of Connecticut in the form of a construction reimbursement grant. Committee members discussed whether to take the additional estimate to the town for referendum, or to wait until July, when the committee will receive official bids for the project.