“We are currently wrapping up our local approvals and will be shortly submitting to the state for their pre-bid authorization,” said Adam Levitus, senior project manager for the construction work. Financing for the new high school and the demolition of the old one has been through a number of modifications. The most recent estimate for the project to tear down the 1971 building and construct a brand new building is $446 million. The work on the new building at 125 Roxbury Road is expected to start in April of 2026, and the structure would be completed in the summer of 2029, Levitus said. The demolition of the old building would take place in 2029 and 2030, Levitus told the Planning Board. “It’s quite a challenge,” said Kemp Morhardt, the lead architect on the project from the SLAM architectural firm.
https://www.stamfordadvocate.com/news/article/ct-stamford-westhill-high-school-21063674.php