One in Three Projects at State Pier Hit Obstacles, Testing Budget and Timeline

Port Authority interim Executive Director Ulysses B. Hammond said that three of nine stages of construction at the State Pier have run into difficulties and run behind schedule in the last month – construction of the south wall of the pier, its toe wall, and the heavy lift platform that will allow for it to be used for offshore wind staging. Hammond said the contractor Kiewit reported that higher than anticipated rock elevations and obstructions have negatively impacted pile driving progress on the pier, which needs to be substantially completed by March 2023 in order for Eversource and Ørsted to use it for construction of their joint offshore wind project, South Fork Wind. Despite the issues, Hammond said the target is still “substantial completion of the project” before Feb. 28, 2023, and final completion by June 2023.

One in Three Projects at State Pier Hit Obstacles, Testing Budget and Timeline

Share This Article: