industry news
Stay updated with the latest developments and insights from across the industry
Eversource upgrades gas lines on Danbury’s Main Street, with repaving work planned for July
The utility provider is working closely with the city of Danbury and the Connecticut Department of Transportation on the project, “and our work will be complete in June to meet DOT’s schedule for their planned work along Main Street,” Ratliff said. Then DOT will take over the project. Iadarola said that under the current schedule for Main Street, DOT is scheduled to mill the street surface on June 28 and pave it on July 11. “A preconstruction meeting is scheduled on June 13 for this work and an update will be given after the meeting,” Iadarola said. And that’s not the only gas work to be completed on Main Street. Additional work along Kennedy Avenue and Rose Street to upgrade the system to a high pressure main is also underway. Officials expected Eversource to complete the Main Street portion of this work this week “with temporary patching of the street surface and sidewalk areas taking place to assure a safe route for Memorial Day parade marchers and viewers,” Iadarola said.
https://www.stamfordadvocate.com/local/article/eversource-upgrading-gas-lines-along-danbury-main-19472496.php
When will Stamford’s Cedar Heights Road bridge be done? 12 months late, officials say.
A project to replace the bridge on Cedar Heights Road is now expected to be finished in November — a year later than initially scheduled. City Engineer Lou Casolo has said that the contractor for the “extremely complex” project, A. Vitti Excavators, has needed to submit plans for handling the flow of the Rippowam River, demolishing the more than 90-year old bridge and supporting utility lines to an inspection firm before moving from one stage of construction to the next. The original completion date was Nov. 30, 2023. A. Vitti Excavators committed to working during the winter and asked for an extension to substantially complete the project by May 31 of this year. Then the date changed to June 30. Cedar Heights Road, which is just south of the Merritt Parkway, has been closed to thru traffic during the project. A detour takes cars along High Ridge Road and Wire Mill Road, where another bridge is in line for construction.
https://www.stamfordadvocate.com/news/article/stamford-cedar-heights-road-bridge-19464639.php
Ørsted-Eversource Partnership Announces Cancellation of Agreement for Charybdis (Updated)
The Offshore Wind Venture partnering Ørsted and Eversource told CT Examiner on Wednesday that the companies had canceled an agreement with Dominion Energy to use the as-yet-unbuilt Charybdis to install turbines off East Coast of the United States. The planned 472-foot vessel would be the first Jones Act compliant vessel for installing offshore turbines, clearing a significant hurdle for domestic offshore development. The spokesman declined to name the alternative vessel or disclose the cost of the agreement. But last August, it was reported that the vessel’s expected cost had risen from $500 million to $625 million, and that delays in its construction meant that Dominion would miss deadlines for the installation of 704-MW Revolution Wind, and 924-MW Sunrise Wind. In March, Ørsted submitted a bid for its latest project, Starboard Wind, a 1,184-MW project that the company planned to assemble off of State Pier.
Ørsted-Eversource Partnership Announces Cancellation of Agreement for Charybdis (Updated)
Meriden receives $975,000 in EPA funds to clean up Church and Morse site downtown
The city will receive $975,240 in federal funding to clean a brownfield and foundation rubble at the former Church and Morse building, the U.S. Environmental Protection Agency announced this week. Funding for the Brownfield Cleanup Grant come from the bipartisan infrastructure law and will be used to cleanup the 0.33-acre vacant parcel. The site was previously used for commercial and industrial purposes, including generating electricity, welding and storage. The site is vacant and contaminated with volatile organic compounds, extractable petroleum hydrocarbons, metals and polycyclic aromatic hydrocarbons. The funds will be used to formalize a community engagement plan. The city’s award is part of $8.9 million in EPA grants to the state to expedite the assessment and cleanup. The grants are through the EPA’s dedicated program and revolving loan fund. The program aims to transform once-polluted vacant and abandoned properties into community assets, while helping to create jobs and spur economic revitalization in overburdened communities.
https://www.ctinsider.com/recordjournal/article/meriden-epa-grant-brownfield-cleanup-19472006.php
UConn trustees approve building of new dorm to house 200 students for its downtown Hartford campus
A plan to build a new dorm for UConn’s regional campus in the heart of downtown Hartford won a key approval Wednesday, with the university’s Board of Trustees voting unanimously to sign a 20-year lease to move the project forward. The new dorm would house 200 students in 50 units to be built inside part of a converted office and retail building at 242 Trumbull St. Developer Shelbourne Global Solutions bought the eight-story building at 242 Trumbull in June; the new dorm will be built inside an annex to the main structure with the address 64 Pratt St. The $28 million needed to convert the 242 Trumbull building into student housing will be funded through a package of state and city loans, plus capital from the building’s owner. The estimated $1.4 million annual deficit incurred by subsidizing the student housing to make it affordable will likely be offset by renting the dorms out during the summer to city corporations seeking to house interns and major employers like Hartford HealthCare, Ritter said.
https://www.stamfordadvocate.com/business/article/uconn-dorm-downtown-hartford-ct-pratt-street-19472046.php
Officials tout CT medical facility that will be partially doctor-owned: ‘Outcomes are better’
Trinity and Johnson Memorial Hospital officials made their case to convert its surgery center in Enfield to a freestanding outpatient facility partially owned by physicians during a public hearing before the state Office of Health Strategy on Wednesday. A request for a certificate of need through OHS calls for a $17.8 million facility at Johnson Memorial Hospital’s Enfield campus that would establish a joint venture dubbed “Enfield Surgery Center,” and to cease surgeries at the hospital in Stafford. “The current operating rooms are undersized and outdated,” said Deborah Bitsoli, Springfield market president of Trinity Health of New England, adding that some surgical towers don’t fit in the Johnson Memorial operating rooms due to limited space and low ceilings. Therefore, a replacement ambulatory surgery center is being built and placed next to the existing surgery center site at 148 Hazard Ave.
https://www.stamfordadvocate.com/journalinquirer/article/ct-johnson-memorial-hospital-trinity-enfield-19471868.php
Danbury career academy to earn millions more in state reimbursement due to increased costs
Local leaders applauded the new funding for the high school, as well as $1.9 million to replace the roof at Ellsworth Avenue Elementary School and $10.43 million to renovate the Danbury High School science labs. Lawmakers also touted a $7.54 million increase in the city’s share of state Education Cost Sharing grant monies. Now, the city will earn 80 percent reimbursement on up to $179.5 million of eligible costs, a $25.5 million increase from what the city initially anticipated, officials said. The estimated cost when Danbury voters approved the project in 2022 was $164 million. The project is still on track to open for the 2025-26 school year, Iadarola said. He said he does not anticipate the total project cost will exceed the $179.5 million level that was set for state reimbursement.
https://www.stamfordadvocate.com/local/article/danbury-career-academy-ct-reimbursement-19459913.php
New $1.3M Norwalk River dock allows Walk Bridge construction, local maritime business to continue
The new $1.3 million state-funded dock allows the Norwalk Seaport Association and Maritime Aquarium’s vessels to continue operating on the Norwalk River amid the $1 billion project to replace the 127-year-old Walk Bridge, according to Walk Bridge project manager Gus Melo. The bridge has failed dozens of times in the last decade to close properly over the waterway, halting marine and rail traffic. The floating concrete dock is bordered by piles that hold it in place and allow it to rise with the tide, Toni said. With a large gap between piles in the middle of the dock, Toni said it will also allow Eversource to move transmission lines underground to make way for the Walk Bridge project. Mayor Harry Rilling said the new dock required collaboration between the association, aquarium, local and state government to allow for the Walk Bridge project and local business to continue.
https://www.stamfordadvocate.com/news/article/norwalk-river-dock-walk-bridge-aquarium-seaport-19468796.php
City Council approves $25M for senior center and health campus in Meriden
The City Council voted 7-5 to add $25 million into the city’s capital improvement plan this week to build a new senior center and health department on Cook Avenue. Mayor Kevin Scarpati introduced the resolution to include the $25 million in the capital improvement budget after vetoing the council’s approved spending plan two weeks ago. At that time, the council failed to garner enough votes to override Scarpati’s veto leading to Monday’s action. The $25 million approved Monday will pay for the cost of hiring an architect to bring several design and cost options before the council to approve or disapprove.
https://www.stamfordadvocate.com/recordjournal/article/city-council-25-million-capital-improvement-19469933.php
East Windsor looks at several options to renovate or reconfigure its schools
With buildings built in the 1950s and ’60s and a declining student population, town and school officials are currently looking into how to renovate or even reconfigure the town’s schools. In February, a facilities study done by the Construction Solutions Group determined that Broad Brook Elementary, East Windsor Middle School, and East Windsor High School are too large for their current enrollment sizes based on state construction standards and guidelines. The options range from renovating all three schools as new and “right sizing” the buildings; consolidating the middle and high schools by using either building and moving the fifth grade to the elementary school; constructing three brand-new schools; renovating all three schools with their current sizes; or doing the needed renovations without changing the size of the schools. The costs range from $94 million to consolidate the middle and high schools using the high school building, to $196 million to renovating all three existing schools as new with their current square footage. Each project would be partially funded by the state.
https://www.stamfordadvocate.com/journalinquirer/article/ct-east-windsor-public-schools-renovations-19454682.php
Connect with us
Contact us
If you believe you have been the victim of wage theft on a public works construction project, please feel free to contact our office. You can also visit the Connecticut Department of Labor’s Wage & Workplace Division’s website to file a complaint here.
