The North Street Bridge is on track to be replaced next summer, but doing the job on a shorter timeline is going to cost up to $700,000 more than originally expected. The Department of Public Works originally projected it would cost $3 million to replace the century-old bridge over at least 18 months, but officials drastically shortened the timeline to just 10 months after residents bemoaned the prospect of facing a year-long traffic jam, among other concerns. DPW asked the BET budget committee for the extra $700,000 on Nov. 13. The request was approved by the budget committee, but it still needs authorization from the full BET and the Representative Town Meeting. Work is now scheduled to begin in March. The first phase, from March to June, will keep the bridge open to traffic with some intermittent disruptions as crews do pre-work, like relocating utilities. The second phase, from June to August, will see the bridge torn down and replaced.