The Connecticut Port Authority said Friday it is working with State Pier contractor Kiewit to remedy what appears to be substandard soil used on a portion of the newly-constructed offshore wind facility. The remedy for the problem, the cost to fix it and who might pay remains in question. The problem was discovered by routine soil testing of the 100-foot long section at the south end of the pier where fill was used to expand its size. The area was once two piers. The soil contains excessive silty material and is not in compliance with the port authority’s contract with Kiewit, said Paul Whitescarver, chairman of the board of directors of the Connecticut Port Authority. Despite the problem, Whitescarver said operations at State Pier remain unaffected. The pier is loaded with parts ― wind turbine blades, nacelles and towers ― that are bound for the waters off Rhode Island as part of Orsted’s Revolution Wind project.