DOT: Norwalk I-95 overpass that was destroyed, demolished after fiery crash to be rebuilt by spring

The new $20 million Fairfield Avenue overpass spanning Interstate 95 is taking shape, with orange safety fencing lining the sides and wood planks paneling the bottom of steel beams. “Now that steel has been installed, we plan to re-open the I-95 south, Route 7 on-ramp lane to its original configuration in early September to ease congestion,” state Department of Transportation Spokesperson Samaia Hernandez said in the statement, noting that DOT aims to reopen the bridge fully by the spring. Construction has moved steadily since the fire and DOT’s goal is to pour the bridge’s deck in October, Hernandez said.

https://www.stamfordadvocate.com/news/article/norwalk-i95-cdot-construction-fairfield-ave-bridge-19727780.php