As we rebuild our crumbling interstate highways, the CDOT deserves credit for learning its ABCs… “accelerated bridge construction.” Over two recent weekends they demolished and replaced two three-lane bridges at exit 17 in Westport with, considering the enormity of the tasks, minimal impact on traffic. The speed of the work on the $104 million project was enhanced by building the replacement bridges in advance so they could literally slide into place after the old bridge was torn down. Just imagine the planning, the measuring and tight tolerances. Yet, the first weekend project (for the northbound bridge) was finished 14 hours earlier than planned. A similar bridge replacement in Stamford on I-95 in 2019 went just as well, with more such projects to come as Federal dollars rebuild our infrastructure.