Wallingford school officials consider options with delays to Sheehan track, field project

The Town Council approved bonding $2 million for the project in late April, and the school board estimated the work would be completed in early September. But the combination of a mandated 30-day waiting period before the purchase order could be issued to the contractor and continued supply distribution issues has pushed that completion date out to October, forcing all sporting events scheduled to take place on the field in September to be rescheduled. The contractor, HI Stone, is “doing a fantastic job,” Deptula said, but because of the supply problems, and the fact that the funding was approved later than anticipated, the work is now expected to be completed the first week of October. But student athletes are not looking forward to not being able to play on their home field in September.