Steelpointe luxury apartment project passes environmental hurdles

After months of delays caused by environmental issues, the developers of the luxury apartment project at the Steelpointe site are now aiming to break ground on the first phase in around 50 days. As reported in early January, the Christophs had hoped construction would already have been well-underway. But things got complicated after it was determined the site, the former location of a steel works and electrical substation, had more ground pollution problems than initially anticipated. The overall goal is to build 1,500 luxury apartments in all. Phase one involves 400 and is estimated to take two years to complete, though Christoph said tenants might be able to move in in stages as the units are finished. “It’s going to be exciting,” Christoph said. “It’s going to be another great year to show off Bridgeport’s waterfront.”